Vamsi Ponnekanti 2b9a360c8b [Getting warning while running db_crashtest]
Summary:
When I run db_crashtest, I am seeing lot of warnings that say db_stress completed
before it was killed. To fix that I made ops per thread a very large value so that it keeps
running until it is killed.

I also set #reopens to 0. Since we are killing the process anyway, the 'simulated crash'
that happens during reopen may not add additional value.

I usually see 10-25K ops happening before the kill. So I increased max_key from 100 to
1000 so that we use more distinct keys.

Test Plan:
Ran a few times.

Revert Plan: OK

Task ID: #

Reviewers: emayanke

Reviewed By: emayanke

CC: leveldb

Differential Revision: https://reviews.facebook.net/D9909
2013-04-04 00:17:05 -07:00
..